Section 6-5-701 - Reliance Upon Specifications

Ask AI about this
A contractor is justified ordinarily in relying upon the plans and specifications that are contained in the contract with an awarding authority. No contractor shall be held civilly liable for work performed on the project, including repairs, construction, or maintenance on behalf of the awarding authority, unless it is shown by a preponderance of the evidence that physical injury, property damage, or death is proximately caused by either of the following:(1) A failure by the contractor to follow the plans and specifications resulting in a dangerous condition.(2) A latent defect which creates a dangerous condition that is the result of the work of the contractor.(Act 2012-225, p. 414, §2; Act 2023-316, §1.)

Source: https://alison.legislature.state.al.us/code-of-alabama?section=6-5-701· Version 2026