Skip to main content
CourtGPT logoCourtGPT
Directory
Law
For Attorneys
Blog
AppointmentsSign InSign Up
Section 32-11-617 - Extra work authorized - payment — Colorado Law | CourtGPT
  1. Home/
  2. Laws/
  3. Colorado/
  4. Title 32 - Special Districts Special District Act (§§ 32-1-101 — 32-1-1807)/
  5. Special Statutory Districts/
  6. Article 11 - Urban Drainage and Flood Control Act/
  7. Part 6 - Special Assessments/
  8. Section 32-11-617 - Extra work authorized - payment
Colorado Legal Code

Section 32-11-617 - Extra work authorized - payment

Ask AI about this
Extra work may arise in connection with any project mentioned in this article and not particularly provided for in the plans, specifications, estimates, bids and contracts; and such extra work shall be performed by the contractor at the direction of the engineer at cost of labor and materials and overhead including superintendence as set forth in the plans, specifications, or construction contract, such amount to be included in the assessment for the project (but not exceeding in the aggregate the estimated maximum special benefits to any tract so assessed) or to be paid out of the general or other funds of the district available therefor, in the discretion of the board.L. 69: p. 793, § 130. C.R.S. 1963: § 89-21-130.