Section 43-1-1404 - Criteria

Ask AI about this
(1) The department may use a design-build contract for a transportation project if the design work for such project must be performed before a potential bidder can develop a price or cost proposal for such project and if the chief engineer of the engineering, design, and construction division determines that using a design-build contract is appropriate. The chief engineer shall consider the following factors in making a determination pursuant to this subsection (1): (a) The extent to which the transportation project requirements are adequately defined;(b) The time constraints for completing the transportation project;(c) The capability and experience of potential design-build firms;(d) The suitability of the transportation project to a design-build contract; and(e) The capability of the department to manage the design-build contract.(2) The department may use a design-build contract regardless of the estimated minimum or maximum cost of a transportation project.L. 99: Entire part added, p. 258, § 1, effective April 9.