(415 ILCS 5/Tit. X heading)\nTITLE X: PERMITS\n(415 ILCS 5/39) (from Ch. 111 1/2, par. 1039)\nSec. 39. Issuance of permits; procedures.\n(a) When the Board has by regulation required a permit for the construction, installation, or operation of any type of facility, equipment, vehicle, vessel, or aircraft, the applicant shall apply to the Agency for such permit and it shall be the duty of the Agency to issue such a permit upon proof by the applicant that the facility, equipment, vehicle, vessel, or aircraft will not cause a violation of this Act or of regulations hereunder. The Agency shall adopt such procedures as are necessary to carry out its duties under this Section. In making its determinations on permit applications under this Section the Agency may consider prior adjudications of noncompliance with this Act by the applicant that involved a release of a contaminant into the environment. In granting permits, the Agency may impose reasonable conditions specifically related to the applicant's past compliance history with this Act as necessary to correct, detect, or prevent noncompliance. granting permits, the Agency may impose reasonable conditions specifically related to the applicant's past compliance history with this Act as necessary to correct, detect, or prevent noncompliance. The Agency may impose such other conditions as may be necessary to accomplish the purposes of this Act, and as are not inconsistent with the regulations promulgated by the Board hereunder. Except as otherwise provided in this Act, a bond or other security shall not be required as a condition for the issuance of a permit. If the Agency denies any permit under this Section, the Agency shall transmit to the applicant within the time limitations of this Section specific, detailed statements as to the reasons the permit application was denied. Such statements shall include, but not be limited to, the following:\n(i) the Sections of this Act which may be violated if the permit were granted;\n(ii) the provision of the regulations, promulgated under this Act, which may be violated if the permit were granted;\n(iii) the specific type of information, if any, which the Agency deems the applicant did not provide the Agency; and\n(iv) a statement of specific reasons why the Act and the regulations re granted;\n(iii) the specific type of information, if any, which the Agency deems the applicant did not provide the Agency; and\n(iv) a statement of specific reasons why the Act and the regulations might not be met if the permit were granted.\nIf there is no final action by the Agency within 90 days after the filing of the application for permit, the applicant may deem the permit issued; except that this time period shall be extended to 180 days when (1) notice and opportunity for public hearing are required by State or federal law or regulation, (2) the application which was filed is for any permit to develop a landfill subject to issuance pursuant to this subsection, or (3) the application that was filed is for a MSWLF unit required to issue public notice under subsection (p) of Section 39. The 90-day and 180-day time periods for the Agency to take final action do not apply to NPDES permit applications under subsection (b) of this Section, to RCRA permit applications under subsection (d) of this Section, to UIC permit applications under subsection (e) of this Section, or to CCR surface impoundment applications under subsection (y) of this Section.\nThe Agency shall publish ection (d) of this Section, to UIC permit applications under subsection (e) of this Section, or to CCR surface impoundment applications under subsection (y) of this Section.\nThe Agency shall publish notice of all final permit determinations for development permits for MSWLF units and for significant permit modifications for lateral expansions for existing MSWLF units one time in a newspaper of general circulation in the county in which the unit is or is proposed to be located.\nAfter January 1, 1994 and until July 1, 1998, operating permits issued under this Section by the Agency for sources of air pollution permitted to emit less than 25 tons per year of any combination of regulated air pollutants, as defined in Section 39.5 of this Act, shall be required to be renewed only upon written request by the Agency consistent with applicable provisions of this Act and regulations promulgated hereunder. Such operating permits shall expire 180 days after the date of such a request. The Board shall revise its regulations for the existing State air pollution operating permit program consistent with this provision by January 1, 1994.\nAfter June 30, 1998, operating permits issued under this shall revise its regulations for the existing State air pollution operating permit program consistent with this provision by January 1, 1994.\nAfter June 30, 1998, operating permits issued under this Section by the Agency for sources of air pollution that are not subject to Section 39.5 of this Act and are not required to have a federally enforceable State operating permit shall be required to be renewed only upon written request by the Agency consistent with applicable provisions of this Act and its rules. Such operating permits shall expire 180 days after the date of such a request. Before July 1, 1998, the Board shall revise its rules for the existing State air pollution operating permit program consistent with this paragraph and shall adopt rules that require a source to demonstrate that it qualifies for a permit under this paragraph.\n(b) The Agency may issue NPDES permits exclusively under this subsection for the discharge of contaminants from point sources into navigable waters, all as defined in the Federal Water Pollution Control Act, as now or hereafter amended, within the jurisdiction of the State, or into any well.\nAll NPDES permits shall contain those terms and aters, all as defined in the Federal Water Pollution Control Act, as now or hereafter amended, within the jurisdiction of the State, or into any well.\nAll NPDES permits shall contain those terms and conditions, including, but not limited to, schedules of compliance, which may be required to accomplish the purposes and provisions of this Act.\nThe Agency may issue general NPDES permits for discharges from categories of point sources which are subject to the same permit limitations and conditions. Such general permits may be issued without individual applications and shall conform to regulations promulgated under Section 402 of the Federal Water Pollution Control Act, as now or hereafter amended.\nThe Agency may include, among such conditions, effluent limitations and other requirements established under this Act, Board regulations, the Federal Water Pollution Control Act, as now or hereafter amended, and regulations pursuant thereto, and schedules for achieving compliance therewith at the earliest reasonable date.\nThe Agency shall adopt filing requirements and procedures which are necessary and appropriate for the issuance of NPDES permits, and which are consistent with the Act t the earliest reasonable date.\nThe Agency shall adopt filing requirements and procedures which are necessary and appropriate for the issuance of NPDES permits, and which are consistent with the Act or regulations adopted by the Board, and with the Federal Water Pollution Control Act, as now or hereafter amended, and regulations pursuant thereto.\nThe Agency, subject to any conditions which may be prescribed by Board regulations, may issue NPDES permits to allow discharges beyond deadlines established by this Act or by regulations of the Board without the requirement of a variance, subject to the Federal Water Pollution Control Act, as now or hereafter amended, and regulations pursuant thereto.\n(c) Except for those facilities owned or operated by sanitary districts organized under the Metropolitan Water Reclamation District Act, no permit for the development or construction of a new pollution control facility may be granted by the Agency unless the applicant submits proof to the Agency that the location of the facility has been approved by the county board of the county if in an unincorporated area, or the governing body of the municipality when in an incorporated area, in which cy that the location of the facility has been approved by the county board of the county if in an unincorporated area, or the governing body of the municipality when in an incorporated area, in which the facility is to be located in accordance with Section 39.2 of this Act. For purposes of this subsection (c), and for purposes of Section 39.2 of this Act, the appropriate county board or governing body of the municipality shall be the county board of the county or the governing body of the municipality in which the facility is to be located as of the date when the application for siting approval is filed.\nIn the event that siting approval granted pursuant to Section 39.2 has been transferred to a subsequent owner or operator, that subsequent owner or operator may apply to the Agency for, and the Agency may grant, a development or construction permit for the facility for which local siting approval was granted. Upon application to the Agency for a development or construction permit by that subsequent owner or operator, the permit applicant shall cause written notice of the permit application to be served upon the appropriate county board or governing body of the municipality that that subsequent owner or operator, the permit applicant shall cause written notice of the permit application to be served upon the appropriate county board or governing body of the municipality that granted siting approval for that facility and upon any party to the siting proceeding pursuant to which siting approval was granted. In that event, the Agency shall conduct an evaluation of the subsequent owner or operator's prior experience in waste management operations in the manner conducted under subsection (i) of Section 39 of this Act.\nBeginning August 20, 1993, if the pollution control facility consists of a hazardous or solid waste disposal facility for which the proposed site is located in an unincorporated area of a county with a population of less than 100,000 and includes all or a portion of a parcel of land that was, on April 1, 1993, adjacent to a municipality having a population of less than 5,000, then the local siting review required under this subsection (c) in conjunction with any permit applied for after that date shall be performed by the governing body of that adjacent municipality rather than the county board of the county in which the proposed site is conjunction with any permit applied for after that date shall be performed by the governing body of that adjacent municipality rather than the county board of the county in which the proposed site is located; and for the purposes of that local siting review, any references in this Act to the county board shall be deemed to mean the governing body of that adjacent municipality; provided, however, that the provisions of this paragraph shall not apply to any proposed site which was, on April 1, 1993, owned in whole or in part by another municipality.\nIn the case of a pollution control facility for which a development permit was issued before November 12, 1981, if an operating permit has not been issued by the Agency prior to August 31, 1989 for any portion of the facility, then the Agency may not issue or renew any development permit nor issue an original operating permit for any portion of such facility unless the applicant has submitted proof to the Agency that the location of the facility has been approved by the appropriate county board or municipal governing body pursuant to Section 39.2 of this Act.\nAfter January 1, 1994, if a solid waste disposal facility, any portion for acility has been approved by the appropriate county board or municipal governing body pursuant to Section 39.2 of this Act.\nAfter January 1, 1994, if a solid waste disposal facility, any portion for which an operating permit has been issued by the Agency, has not accepted waste disposal for 5 or more consecutive calendar years, before that facility may accept any new or additional waste for disposal, the owner and operator must obtain a new operating permit under this Act for that facility unless the owner and operator have applied to the Agency for a permit authorizing the temporary suspension of waste acceptance. The Agency may not issue a new operation permit under this Act for the facility unless the applicant has submitted proof to the Agency that the location of the facility has been approved or re-approved by the appropriate county board or municipal governing body under Section 39.2 of this Act after the facility ceased accepting waste.\nExcept for those facilities owned or operated by sanitary districts organized under the Metropolitan Water Reclamation District Act, and except for new pollution control facilities governed by Section 39.2, and except for fossil fuel or operated by sanitary districts organized under the Metropolitan Water Reclamation District Act, and except for new pollution control facilities governed by Section 39.2, and except for fossil fuel mining facilities, the granting of a permit under this Act shall not relieve the applicant from meeting and securing all necessary zoning approvals from the unit of government having zoning jurisdiction over the proposed facility.\nBefore beginning construction on any new sewage treatment plant or sludge drying site to be owned or operated by a sanitary district organized under the Metropolitan Water Reclamation District Act for which a new permit (rather than the renewal or amendment of an existing permit) is required, such sanitary district shall hold a public hearing within the municipality within which the proposed facility is to be located, or within the nearest community if the proposed facility is to be located within an unincorporated area, at which information concerning the proposed facility shall be made available to the public, and members of the public shall be given the opportunity to express their views concerning the proposed facility.\nThe Agency may issue a permit oposed facility shall be made available to the public, and members of the public shall be given the opportunity to express their views concerning the proposed facility.\nThe Agency may issue a permit for a municipal waste transfer station without requiring approval pursuant to Section 39.2 provided that the following demonstration is made:\n(1) the municipal waste transfer station was in existence on or before January 1, 1979 and was in continuous operation from January 1, 1979 to January 1, 1993;\n(2) the operator submitted a permit application to the Agency to develop and operate the municipal waste transfer station during April of 1994;\n(3) the operator can demonstrate that the county board of the county, if the municipal waste transfer station is in an unincorporated area, or the governing body of the municipality, if the station is in an incorporated area, does not object to resumption of the operation of the station; and\n(4) the site has local zoning approval.\n(d) The Agency may issue RCRA permits exclusively under this subsection to persons owning or operating a facility for the treatment, storage, or disposal of hazardous waste as defined under this Act. (d) The Agency may issue RCRA permits exclusively under this subsection to persons owning or operating a facility for the treatment, storage, or disposal of hazardous waste as defined under this Act. Subsection (y) of this Section, rather than this subsection (d), shall apply to permits issued for CCR surface impoundments.\nAll RCRA permits shall contain those terms and conditions, including, but not limited to, schedules of compliance, which may be required to accomplish the purposes and provisions of this Act. The Agency may include among such conditions standards and other requirements established under this Act, Board regulations, the Resource Conservation and Recovery Act of 1976
Illinois Legal Code