Skip to main content
CourtGPT logoCourtGPT
Directory
Law
For Attorneys
Blog
AppointmentsSign InSign Up
§ 278.212 — Kentucky Law | CourtGPT
  1. Home/
  2. Laws/
  3. Kentucky/
  4. Chapter 278 - Public Service Commission/
  5. § 278.212
Kentucky Legal Code

§ 278.212

Ask AI about this
278.2 12 Filing of plans for electrical interconnection with merchant electric generating facility -- Costs of upgrading existing grid. (1) No utility shall begin the construction or installation of any property, equipment, or facility to establish an electric al interconnection with a merchant electric generating facility in excess of ten megawatts (10MW) until the plans and specifications for the electrical interconnection have been filed with the commission. (2) Notwithstanding any other provision of law, any costs or expenses associated with upgrading the existing electricity transmission grid, as a result of the additional load caused by a merchant electric generating facility, shall be borne solely by the person constructing the merchant electric generating facility and shall in no way be borne by the retail electric customers of the Commonwealth. Effective: April 24, 2002 History: Created 2002 Ky. Acts ch. 365, sec. 11, effective April 24, 2002.