Skip to main content
CourtGPT logoCourtGPT
Directory
Law
For Attorneys
Blog
AppointmentsSign InSign Up
§ 460.565 — Michigan Law | CourtGPT
  1. Home/
  2. Laws/
  3. Michigan/
  4. Chapter 460 - Public Utilitiesact 3 of 1939 - Michigan Public Service Commission (460.1 - 460.11)/
  5. Statute Act 30 of 1995/
  6. § 460.565
Michigan Legal Code

§ 460.565

Ask AI about this
460.565 Transmission line; certificate required. Sec. 5. An electric utility, affiliated transmission company, or independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under section 4 until the commission issues a certificate for that transmission line. Except as otherwise provided in section 9, a certificate of public convenience and necessity under this act is not required for constructing a new transmission line other than a major transmission line or for reconstructing, repairing, replacing, or improving an existing transmission line, including the addition of circuits to an existing transmission line. History: 1995, Act 30, Imd. Eff. May 17, 1995 ;-- Am. 2004, Act 198, Imd. Eff. July 12, 2004