28-2-723. Construction contracts requiring lien or bond waiver void. A construction contract may not contain provisions requiring a contractor, subcontractor, or material supplier to waive the right to a construction lien or a right to a claim against a payment bond before the contractor, subcontractor, or material supplier has been paid for the labor, materials, or both labor and materials, furnished by the contractor, subcontractor, or material supplier. History: En. Sec. 1, Ch. 119, L. 1999.
Montana Legal Code
§ 28-2-723
Source: https://mca.legmt.gov/bills/mca/title_0280/chapter_0020/part_0070/section_0230/0280-0020-0070-0230.html· Version 2025