Montana Legal Code

§ 71-3-562

Ask AI about this
71-3-562. Limitation on actions. All actions under this part must be commenced within 2 years from the date of the filing of the lien. History: En. Sec. 2139, C. Civ. Proc. 1895; re-en. Sec. 7299, Rev. C. 1907; amd. Sec. 1, Ch. 127, L. 1921; re-en. Sec. 8348, R.C.M. 1921; re-en. Sec. 8348, R.C.M. 1935; R.C.M. 1947, 45-510; Sec. 71-3-505, MCA 1985; redes. 71-3-562 by Code Commissioner, 1987.