75-2-505. Small project review requirement. The department shall review a permit application within 5 working days of receipt of a complete application and an appropriate fee for an asbestos project that: (1) involves more than 10 square feet but less than 160 square feet in surface area; (2) involves more than 3 linear feet but less than 260 linear feet of pipe; or (3) involves more than 3 cubic feet but less than 35 cubic feet of volume. History: En. Sec. 2, Ch. 309, L. 2015.