Except as otherwise provided in NRS 226.826, none of the provisions of NRS 338.020 to 338.090, inclusive, apply to: 1. Apprentices recorded under the provisions of chapter 610 of NRS. 2. Any contract for a public work whose estimated cost is less than $100,000. A unit of the project must not be separated from the total project, even if that unit is to be completed at a later time, in order to lower the estimated cost of the project below $100,000. [9:139:1937; 1931 NCL § 6179.59] + [8:169:1941; 1931 NCL § 6179.62]—(NRS A 1967, 34; 1985, 2041; 2003, 2416; 2013, 1026; 2015, 2654; 2017, 4140; 2019, 933; 2021, 3816; 2023, 35th Special Session, 44)
Nevada Legal Code