Skip to main content
CourtGPT logoCourtGPT
Directory
Law
For Attorneys
Blog
AppointmentsSign InSign Up
Statute 338 490 — Nevada Law | CourtGPT
  1. Home/
  2. Laws/
  3. Nevada/
  4. Chapter 338 - Public Worksnrs 338.010 - Definitions/
  5. Statute 338 490
Nevada Legal Code

Statute 338 490

Ask AI about this
Any release or waiver required to be provided by a contractor, subcontractor or supplier to receive a progress payment or retainage payment must be: 1. Conditional for the purpose of receiving payment and shall be deemed to become unconditional upon the receipt of the money due to the contractor, subcontractor or supplier; and 2. Limited to claims related to the invoiced amount of the labor, materials, equipment or supplies that are the subject of the progress bill or retainage bill. (Added to NRS by 1999, 1989)