49-34A-84. Requirements for refund.The refund pertains only to project costs incurred and paid after July 1, 2001. The refund pertains only to project costs that were incurred and paid within thirty-six months of the approval of the application required by §§49-34A-80 to 49-34A-92, inclusive. No refund may be made unless:(1)The project costs exceed five hundred thousand dollars; and(2)The person applying for the refund obtains a permit from the secretary as set forth in §49-34A-86. Source: SL 2001, ch 257, §5.